PROJECT
Schedule
Spring 2018: Land secured with original developer
Summer 2018: Land purchased by ABO Wind
September 2018: Stakeholder consultation begins
December 2018: Additional land secured (land base extended)
December 2018: First meteorological mast erected
Spring 2018: Environmental studies begin
March 27, 2019: First open house
June 2019: Entered AESO Queue
November 28, 2019: Second open house
December 2019: Second meteorological mast erection
Fall 2020: AUC Application
Winter 2022: AUC Approval
Spring 2023: Anticipated date of construction
Fall 2024: Target Commercial Operations Date (COD)
2048: Anticipated decommissioning and reclamation
Schedule is preliminary and subject to change.